Projects

Xindadong Textile,
Vietnam
​
12.75 MWp PPA
Total Roof Space: 75,000 sqm
Construction Permitting: 3 months
Construction: 6 months
Status: Under Operation

Fukang Technology,
Vietnam
​
11.00 MWp ELA
Total Roof Space: 131,000 sqm
Construction Permitting: 1.5 month
Construction: 4 months
Status: Under Operation

Duy Tan Plastics,
Vietnam
​
2.17 MWp PPA
Total Roof Space: 16,000 sqm
Construction Permitting: 2 months
Construction Period: 3.5 months
Status: Under Operation

GSK,
Vietnam
​
1.63 MWp ELA
Total Roof Space: 11,400 sqm
Construction Permitting: 2 months
Construction: 3.5 months
Status: Under Operation

Ducati,
Thailand
​
1.00 MWp PPA
Total Roof Space: 29,043 sqm
Construction Permitting: 1 month
Construction: 3.5 months
Status: Under Operation

Universal Alloy Corporation Vietnam,
Vietnam​
4.30 MWp PPA
Total Roof Space: 27,767 sqm
Construction Permitting: 9.5 months
Construction: 5.5 months
Status: Under Operation

Terumo BCT Vietnam,
Vietnam
​
2.01 MWp PPA
Total Roof Space: 15,099 sqm
Construction Permitting: 8.5 months
Construction: 10 months
Status: Under Operation

Maple Tree – Vivo City Commercial Building,
Vietnam
0.75 MWp PPA
Total Roof Space: 15,141 sqm
Construction Permitting: 1 months
Construction: 5 months
Status: Under Operation

Schindler Vietnam,
Vietnam
​
0.25 MWp PPA
Total Roof Space: 4,592 sqm
Construction Permitting: 2 months
Construction: 1.5 months
Status: Under Operation

Motul Vietnam,
Vietnam
​
0.28 MWp PPA
Total Roof Space: 6,170 sqm
Construction Permitting: 2 months
Construction: 4.5 months
Status: Under Operation

Zhong Jian Vietnam,
Vietnam
​
1.24 MWp PPA
Total Roof Space: 22,141 sqm
Construction Permitting: 3 months
Construction: 3 months
Status: Under Operation

Juwon Vietnam,
Vietnam
​
1.23 MWp PPA
Total Roof Space: 8,496 sqm
Construction Permitting: 2 months
Construction: 2.5 months
Status: Under Operation

Long Rich Vietnam,
Vietnam
​
1.19 MWp PPA
Total Roof Space: 11,024 sqm
Construction Permitting: 2 months
Construction: 3.5 months
Status: Under Operation
![ACCV 09 Long Fa [Not Post on website].jpg](https://static.wixstatic.com/media/b359ab_76f002f864b3417bb1cce3ac02c0f0ff~mv2.jpg/v1/crop/x_188,y_80,w_958,h_538/fill/w_411,h_230,al_c,q_80,usm_0.66_1.00_0.01,enc_avif,quality_auto/ACCV%2009%20Long%20Fa%20%5BNot%20Post%20on%20website%5D.jpg)
Long Fa Vietnam,
Vietnam​
​
2.50 MWp PPA
Total Roof Space: 20,800 sqm
Construction Permitting: 2 months
Construction: 1 months
Status: Under Operation

Freeview Vietnam,
Vietnam
​
1.02 MWp ELA
Total Roof Space: 7,770 sqm
Construction Permitting: 2 months
Construction: 3 months
Status: Under Operation